The homepage refuses to publish a timeline because review, utilities and method dominate, and they vary. This tool still lets you add the weeks. The defaults are planning placeholders. They are not a promise for your city.
Permit reviewis the clock you do not controlDesign and permitting are sequential. Modular shortens time on site, not time at the counter. The homepage already says we do not publish a national ADU schedule. The defaults here are labeled as editorial so they cannot be mistaken for one.
Type weeks for design, permit and planning review, site and foundation, building, and finishes through certificate of occupancy. The total is the sum, as if the phases do not overlap.
On the editorial defaults (8 + 12 + 4 + 16 + 4) that is 44 weeks, and permit review is called out as the uncontrolled clock. Replace every default with what your designer and your city have actually said. HyreADU does not schedule crews.
Five phases, summed
Defaults are placeholders. Overwrite them. Nothing is emailed.
—Sum of the weeks you typed
—Permit / planning review
—Longest line
—Overlap
What this assumed—
Editorial defaults are planning placeholders, not a local schedule. HyreADU does not schedule crews.
There is a 60-day clock in statute and a 162-day median in the data
Both are true. They are not in conflict, because they do not measure the same span — and understanding why is worth more to your schedule than either number on its own.
The statute runs from a COMPLETED application. These medians run from the published submitted, filed or received date. Every day between those two events sits inside the bars and outside the clock.LADBS Building and Safety — Building Permits Issued from 2020 to Present (N); DataSF Building Permits (DBI Permit Tracking System extract); Marin County Community Development Agency — Building Permit (mkbn-caye). Retrieved 2026-09-05.
The statute. Under Gov. Code § 66317(a)(3), as amended by SB 543 (Stats. 2025, ch. 520, effective 1 January 2026), the permitting agency "The permitting agency shall either approve or deny the application to create or serve an accessory dwelling unit within 60 days from the date the permitting agency receives a completed application if there is an existing single-family or multifamily dwelling on the lot." And if it does not: If the local agency has not approved or denied the completed application within 60 days, the application is deemed approved.
If the applicant requests a delay, the 60 days are tolled for the length of the delay.
The observed durations. Los Angeles: median 162 calendar days across 27,188 non-supplemental ADU building permits, with an interquartile range of 79 to 301 days and 19% taking more than a year. Unincorporated Marin: median 174.5 across 472.
San Francisco: median 445 across 1,713 issued permits, IQR 276 to 707, and 62% over a year. All three are HyreADU calculations on the cities’ own published extracts; the method is on the permit-times research page.
Say the caveat plainly, because it is the whole point. These are calendar days from the published application-side date to issuance, on permits that issued.
The statutory 60 days runs from a COMPLETED application, and none of the three extracts marks the completeness determination.
The gap between the two therefore includes every day an applicant spent curing an incomplete set, paying fees, answering plan-check comments, or asking for delay.
A median above 60 days is not, by itself, a finding that a city missed the shot clock.
So what is the gap made of? Everything between hitting submit and the agency holding a set it considers complete: missing documents, unpaid fees, structural sheets that were not signed, energy calculations that were not attached, plan-check comments that took three weeks to answer, and any delay the applicant asked for — which the statute expressly tolls.
None of that is the counter being slow. Some of it certainly is queue time as well; the extracts do not let anyone separate the two, and we will not pretend otherwise.
The inference that is actually useful. Our reading is that if a large part of the gap is time spent curing an incomplete set, then it is time your team controls.
That reframes what you are buying when you hire a designer. The most valuable thing a designer does on an ADU may not be the elevation — it may be submitting a set complete enough that the statutory clock actually starts on the day you file.
This is analysis rather than a finding in the data, and it is labeled as such, but it is consistent with everything below.
And a note on what a wide distribution means for planning. A median of 162 days with a quarter of cases above 301 is not a duration you can put in a contract.
The honest way to use it is as a distribution: plan against the median, hold a reserve against the upper quartile, and do not build a financing structure whose viability depends on landing near the fast end.
The clock does not start when you submit. It starts when you are complete
The completeness rule is the single most consequential sentence in the statute for your schedule, and a 2025 amendment gave it a clock of its own.
What SB 543 added. SB 543 added a completeness clock: a written completeness determination within 15 business days, a list of what is missing, a limited resubmittal, and a deemed-complete consequence if the agency misses the determination.
An appeal of incompleteness or of a denial gets a final written determination within 60 business days (§ 66317(d)). Those are business days; the 60-day decision is not labeled as business days. The cite is Gov. Code § 66317(a)(2).
Read the units carefully. The completeness determination is 15 business days. The appeal route is in business days too. The 60-day decision is not labeled as business days.
Business days and calendar days are different quantities, and a fortnight of public holidays sits differently inside each of them. When you put dates in a schedule, convert deliberately rather than assuming.
What the amendment gives you that you did not have. Before a completeness clock existed, an application could sit in an ambiguous state — filed but not accepted — for as long as it took, and nothing was running.
A written determination inside a fixed window, with a list of what is missing and a deemed-complete consequence if the agency misses it, converts that ambiguity into two dated events you can hold people to.
That is a genuine change in your position, and it is recent enough that a lot of guidance has not caught up with it.
What it does not do. It does not stop the list of missing items being long, and it does not stop the resubmittal cycle being where the weeks go. The remedy for that is upstream: a complete set on day one. There is no procedural device that substitutes for documents that exist.
And cite it correctly, because that is a test of your sources. SB 477 (Stats. 2024, ch. 7), an urgency measure effective 25 March 2024, recodified State ADU Law out of Government Code § 65852.2 into Chapter 13 of Division 1 of Title 7, sections 66310 through 66342.
A guide that still cites § 65852.2 is citing a repealed numbering.
State ADU law now sits at Gov. Code §§ 66310–66342, and the fee section moved again in 2026: The ADU fee rules that used to sit in former § 65852.2, and then at § 66324, were renumbered to § 66311.5 by SB 543 (Stats. 2025, ch. 520, effective 1 January 2026).
A handout, a consultant or a checklist still working from § 65852.2 has not been revised since March 2024 — and the completeness clock described above did not exist then. That is not a gotcha.
It is a fast way to find out how current the advice in front of you is.
The same city, four review routes, and medians that differ by months
Los Angeles publishes the business unit that handled each permit. The spread between them is larger than most of the choices you will agonise over. The last column is what a route’s median is really telling you.
The bars are not error bars. Each shows where the middle half of permits on that route actually landed — half of all cases fall inside the bar, a quarter below it and a quarter above.LADBS Building and Safety — Building Permits Issued from 2020 to Present (N). Retrieved 2026-09-05.
Review route (LADBS business unit)
Permits
Median days
IQR
Share decided within 60 days
What that number is really telling you
Plan Check at Counter
3,442
67
6–178
48%
The fastest route by a wide margin, and the one with the largest share resolved at or near zero days. Our reading is that this is selection rather than speed: simple scopes that can be checked across a counter go here. It is not a service level you can request for a complex set.
Expanded Counter Plan Check
12,989
128
63–231
24%
The largest single group in the extract. A median of about four months with a quarter of cases beyond eight is the realistic center of gravity for an ordinary ADU in this city.
Regular Plan Check
10,548
239
145–414
4%
Nearly 172 days of median difference against the counter route — HyreADU subtraction on the two published medians. If your project is heading here, the schedule you were quoted from someone else’s counter-route experience does not apply to you.
Appointment Plan Check
209
242
119–527
11%
A small group — 209 permits — with the widest interquartile range of the four. Small groups produce unstable statistics, and a wide IQR on a small n is a reason to treat the median as indicative rather than as a planning figure.
LADBS Building and Safety — Building Permits Issued from 2020 to Present (N). HyreADU calculation, non-supplemental ADU building permits, n = 27,188. Retrieved 2026-09-05. These are calendar days from the published application-side date to issuance, not the statutory span.
Permit type moves the schedule too, and in the direction you would expect
The same extract, cut by the permit type rather than the review route. It is the closest published proxy this site has to "conversion versus new building".
Illustrative rendering of three categorical values, not a time series. The line exists to make the three medians easy to compare at a glance and carries no meaning between the points.LADBS Building and Safety — Building Permits Issued from 2020 to Present (N). Retrieved 2026-09-05.
The three published categories. Bldg-Alter/Repair: median 102 days across 9,683 permits, IQR 38–203, 35% decided within 60 days. Bldg-New: median 218 days across 9,145 permits, IQR 130–373, 7% decided within 60 days. Bldg-Addition: median 175 days across 8,360 permits, IQR 94–316, 14% decided within 60 days.
What that ordering is worth to you. The heaviest category is new construction, which is what a detached ADU usually is, and the lightest is alteration and repair, which is where a lot of conversion work lands.
So the form of the unit you choose is also a choice about the queue you join. That is a real planning input, and it is one people make on cost and aesthetics without noticing that it moves the calendar too.
Be careful about what it does not prove. Permit type is a coding convention in a municipal system, not a description of your building.
A given ADU can be coded more than one way, the categories overlap in practice, and the difference in medians is confounded with scope, complexity and the review route that scope attracts.
We publish the cut because the direction is stable and useful; we do not publish it as a causal claim that changing the code on your form would change your date.
And it does not transfer between cities. This is one city’s coding of one city’s permits.
San Francisco’s median of 445 days across 1,713 permits, with 62% over a year, tells you that the between-city variation dwarfs the between-type variation.
Ask your own counter for their current ADU review times and type that into the form.
Two statutory routes that are genuinely faster, and who they reach
Both are real, both are current, and both are narrower than the summary you will have read elsewhere.
The 30-day pre-approved plan route (Cal. Gov. Code § 65852.27)
A complete application for a DETACHED ADU that uses a plan preapproved in the current triennial California Building Standards Code cycle, or a plan identical to one the agency already approved in that cycle, must be approved or denied ministerially within 30 days.
By its terms that clock does not reach attached ADUs, garage conversions or JADUs unless a local program separately covers them.
AB 1332 (Carrillo, 2023), effective 2025-01-01. Read the scope sentence twice: it is a DETACHED unit, using a plan preapproved in the current triennial code cycle or identical to one the agency already approved in that cycle.
A garage conversion, an attached unit or a JADU does not get there on the strength of this section alone.
The separate question is whether your agency actually has a usable catalog — a statutory duty to develop a program and a posted set of plans someone can build from are not the same thing.
What exists is covered on the pre-approved plans research page. Ask the counter directly, and ask when the catalog was last revised against the current code cycle, because a plan from the previous cycle does not qualify.
The coastal permit, now concurrent (Gov. Code § 66329)
A local government with a certified local coastal program must approve or deny a coastal development permit for an ADU within 60 days of a completed application, concurrently with the § 66317 decision, without a public hearing, and not subject to appeal under Public Resources Code § 30603.
Where there is no certified LCP the Coastal Commission carries the same 60-day duty, with a deemed-approved consequence if it misses.
That is AB 462 (Stats. 2025, ch. 491, effective 10 October 2025).
Historically the coastal development permit was the longest pole in the tent for anyone inside the coastal zone, precisely because it ran after and separately from the building decision.
A concurrent 60 days with no public hearing is a structurally different process, not a faster version of the old one.
If you are in the coastal zone and were told a coastal permit means a year, find out when that advice was formed. It may predate the amendment.
And one route that is not a shortcut
Deemed approval. If the agency misses the 60 days on a completed application, the application is deemed approved — but that is a remedy, not a plan. It depends on the clock having started, which depends on completeness, which is the thing most often in dispute. Nobody should schedule a project around the counter failing.
The useful version of this provision is as leverage in a conversation about dates, and as a reason to document the completeness determination when you receive it. Keep the dated correspondence.
Two cities are missing from this data, and that is a finding
We could have substituted a proxy for them. It would have been the least honest thing on the page.
City of Sacramento. The published issued-permit layer has Status_Date (the issued/status date) and Application as a permit number (e.g. RES-2600002). No application/filed/submitted date field is published. Duration cannot be computed. Checked 2026-09-05.
City of San José. CKAN resources publish ISSUEDATE and FINALDATE. No application, filed, received or submitted date. Duration cannot be computed. Checked 2026-09-05.
Why this matters beyond these two cities. A duration needs two dates. Where a portal publishes only the issued date, no amount of analysis recovers the missing one, and any figure produced anyway is an assumption dressed as a measurement.
Both of these are large jurisdictions with active ADU programs, so their absence is not a rounding issue in the coverage — it is a real limit on what this site can say about California as a whole.
What you can do about it for your own city. Ask the building department directly for current ADU review times, in weeks, for a complete set, and ask them to distinguish first review from back-check.
That single question produces a better input for the form above than any statewide figure could, because it comes from the people who will actually do the review.
And treat the absence as a signal about other sources. If a guide publishes a confident permit-duration figure for a city whose open data contains no application date, ask where the number came from. Sometimes there is a good answer. Often there is not.
The permit clock ends and the construction clock starts
The state publishes both permits and completions, and the lag between them is its own schedule — one this form’s later phases are trying to describe.
The published lag. Among matched projects in California Department of Housing and Community Development, Housing Element Annual Progress Report, Table A2’s reporting, the median lag from permit to completion is 1 year: 29% report a completion in the permit year, 79% within one year and 94% within two.
Which puts the permit phase in proportion. If the median permit takes months and the median build takes about a year after that, then a project is a multi-year commitment even when nothing goes wrong. The form above sums five phases without overlap precisely so the total is uncomfortable enough to be realistic.
And the part nobody schedules for. 41% of ADU permit units issued between 2018 and 2023 — 46,944 of 114,651 — have no matching completion in the file.
Read that with the caveat attached: These are reported APR rows, not a physical census of construction.
An unmatched permit may be a unit still under construction, an abandoned project, a unit completed without a reported certificate, or a project whose identifier changed between the permit row and the completion row.
The direction is robust; the exact rate is a reporting artefact as much as a construction one.
Our reading of what that means for a timeline. The schedule risk on an ADU is not mainly that each phase runs a bit long.
It is that the project stops somewhere after approval — which is the point at which somebody has to produce the money. A timeline that assumes financing is arranged is modeling the easy case. Arrange the money before the fees, not after.
A note on inspections. Passing inspections are already inside a competent building-phase estimate. Failed ones are not, and they are the reliable source of schedule surprise in the finishes phase.
Ask your builder how many inspections they expect, what the usual re-inspection interval is at your department, and who pays for a re-inspection fee. That last one belongs in the contract, not in a conversation held after the failure.
The order that protects the schedule
Most schedule damage is done in the first three weeks, by starting the wrong phase first.
1
Talk to planning before you buy drawings
Ask which statutory route your project will be processed under, what their current ADU review times are, and what they consider a complete submittal. Paying for a design of a building that will not fit the route is the expensive mistake this whole site is organized around preventing, and the conversation is free.
2
Get the utility figures in writing at the same time
Connection and capacity charges are NOT impact fees. Under § 66311.5(b), an ADU is not a new residential use for connection-fee purposes unless it is built together with a new single-family dwelling — but the utility can still bill a connection or capacity charge, and that bill is outside the impact-fee prohibition entirely.
These are not on the building department’s clock at all, and a service upsize can have a lead time that is longer than the permit.
Find out early enough that it can run in parallel rather than in series.
3
Buy completeness, not just drawings
When you engage a designer, ask explicitly what is included in the submittal set: structural, energy compliance, a site plan the department will accept, and the response to plan-check comments. A set that is missing pieces does not start the statutory clock, and the weeks spent assembling the rest are weeks you paid for twice.
4
Diary the completeness determination
15 business days for a written determination, with a deemed-complete consequence if the agency misses it. Put the date in a calendar on the day you file, and keep the dated correspondence. This is the event that starts everything else.
5
Answer plan-check comments as a priority, not as they arrive
Our reading of the gap between the statutory clock and the observed medians is that response time is a large part of it.
A comment set that sits for three weeks on a designer’s desk is three weeks added to your project with nobody’s name on it. Agree a turnaround commitment in writing before it happens.
6
Do not let the construction phase start before the money is closed
Approval is the cheap half. The completion gap in the state’s own reporting is what happens to projects that reach approval without the finance in place.
What to ask, and what a good schedule answer sounds like
Ask these of the counter and of your builder. A vague answer to any of them is itself the answer.
Which review route will my application take, and what is that route’s current time?
In Los Angeles the published medians by review route range from 67 to 242 days. Being told "about three months" without being told which route is being described is not information you can plan with.
What do you consider a complete submittal, in a list?
Ask for it in writing before you file. The completeness clock only helps if the set is right on the first pass, and the department will usually tell you exactly what they want if you ask before rather than after.
Is there a pre-approved plan catalog, and is it current-cycle?
A detached unit on a current-cycle preapproved plan carries a 30-day ministerial decision under Cal. Gov. Code § 65852.27. A catalog that has not been revised against the current triennial code cycle does not qualify, so ask about the cycle rather than about the catalog.
What is your turnaround commitment on plan-check comments?
Ask the designer, and get a number. This is one of the few parts of the permit phase that is contractually yours to control, and it is the one most often left unspecified.
What is the utility lead time, and is the existing service adequate?
Both utilities, separately, in writing. An upsize is a different order of both cost and time from a straightforward connection, and it runs on nobody else’s schedule.
Do not put the form’s total in a contract
It sums five numbers you typed with no overlap and no allowance for a failed inspection, a factory queue or a utility. It is a planning sketch. A liquidated-damages schedule needs a builder who has committed to dates, not a calculator.
Do not read the observed medians as anyone missing the clock
These are calendar days from the published application-side date to issuance, on permits that issued. The statutory 60 days runs from a COMPLETED application, and none of the three extracts marks the completeness determination.
The gap between the two therefore includes every day an applicant spent curing an incomplete set, paying fees, answering plan-check comments, or asking for delay. A median above 60 days is not, by itself, a finding that a city missed the shot clock.
What this tool cannot do
Specific, not boilerplate. These are the things a reader might reasonably expect from a timeline planner and will not get here.
It cannot give you a completion date
It adds five numbers you typed, with no overlap assumed. That is a conservative sum, not a forecast. Nothing in it knows your department’s backlog, your builder’s other jobs, or whether your structural engineer is on holiday in the month your comments land.
The defaults on the form are labeled editorial placeholders for exactly this reason. They are there so the arithmetic runs before you have real numbers, not so you can use them.
It cannot tell you where in the distribution you will land
In Los Angeles the middle half of non-supplemental ADU permits fell between 79 and 301 days, and 19% took more than a year. A single number typed into a permit field cannot represent that, and no calculator can tell you which end of it your project belongs to.
It holds no data for most of California, and none outside it
Three jurisdictions are measured on this site. Two large cities are excluded because they publish no application-side date. Everywhere else, we have nothing, and we would rather say so than generalise from three data points to fifty states.
It cannot model overlap, float or a real critical path
Some site work genuinely overlaps late design. Long-lead items — windows, a kitchen, a factory slot — sit outside the phase structure entirely. If your builder has produced a real program with dependencies, that document is better than this one, and this page is best used as a sanity check against it.
It does not know whether your project will finish at all
The unmatched share in the state’s own cohort reporting is 41% of permit units between 2018 and 2023. A timeline is a model of the projects that continue. It has nothing to say about the ones that stop, and stopping is the commonest schedule outcome nobody plans for.
It is not legal advice about your application
Statutes are quoted at the numbering current on 2026-09-05 and ADU law has changed in each of the last several sessions. Local implementation, overlays, coastal zones and fire severity zones all sit on top of the state floor. The counter is free.
The vocabulary of a permit schedule
Shot clock
The informal name for the statutory decision deadline. Under Gov. Code § 66317(a)(3) it is 60 days from a completed application, with deemed approval if the agency misses and tolling for applicant-requested delay.
Completed application
The event that starts the clock — not the day you filed. 15 business days for a written completeness determination under Gov. Code § 66317(a)(2), with a list of what is missing and a deemed-complete consequence.
Deemed approved
The consequence of the agency missing the decision deadline on a completed application. A remedy to know about, not a schedule to rely on.
Tolling
Pausing the clock. If the applicant requests a delay, the statute stops the 60 days for the length of it. Every day you take to answer is a day the agency does not owe you.
Plan check
The review of the submitted set against code. Comments come back; you answer them; the set is checked again. This cycle is where most of the gap between the statutory clock and the observed medians lives.
Back-check
The re-review after comments are answered. Ask your department whether their quoted review time covers first review only or the whole cycle — the two answers can differ by months.
Interquartile range (IQR)
The 25th to 75th percentile — where the middle half of cases fell. In Los Angeles that is 79 to 301 days. It is a better planning object than a median because it shows the spread you are actually exposed to.
Application-to-issuance duration
calendar days from application/filed/received date to issued date, on issued ADU building permits only. It is a longer span than the statutory clock measures, which is why a median above 60 days is not a compliance finding.
Permit-to-completion lag
The gap between a permit and a reported completion. Among matched projects the median is 1 year, with 79% within one year.
When the schedule is the reason to wait
Some totals should stop a project rather than start one. These are the ones worth taking seriously.
When the finance has a shorter fuse than the permit. If a bridging facility, a rate lock or an interest-only period expires inside the range the observed distributions describe, the schedule risk has become a financing risk.
Waiting until the money is arranged on a longer horizon is a legitimate decision, and it is cheaper than discovering the mismatch halfway through plan check.
When the only version that works is the fast end of the distribution. A plan that requires you to land near the 25th percentile is not a plan, it is a hope with dates on it. If the project only works at the fast end, it does not work.
When you have not had the planning conversation yet. Starting the design clock before feasibility is the classic expensive sequencing error, and it is the one this page most wants to prevent. The conversation costs a phone call; the drawings do not.
When a household event sits inside the window. If the reason for the ADU is a relative arriving on a date, then the honest question is whether a multi-year process reaches that date at all, and what the fallback is if it does not.
That is a family question rather than an arithmetic one, and it deserves to be asked before the fees are paid rather than after.
What we are, once. HyreADU does not design, permit or build accessory dwelling units. It does not appraise, lend, invest, let property or prepare taxes, it does not rank or refer contractors, and it takes no referral fee from anyone who does any of those things.
That is what allows these tools to conclude that the numbers do not work, that the answer is to keep the garage, or that the honest next step is a question at the planning counter rather than a deposit.
We hold no dataset of ADU bids, quotes or contracts. Every dollar figure on this site is a named third party’s published figure, arithmetic we performed on one and have labeled as ours, or a number you typed in.
How this calculator works
Total weeks = design + permit review + site + building + finishes. No overlap is assumed. The longest line is reported so you can see which phase you typed as the bottleneck.
Permit review is always restated, even when it is not the longest, because it is the one you cannot crash with more money in the same way you can crash labor.
The defaults (8, 12, 4, 16, 4) are editorial. They are not a survey of completed ADUs. The homepage’s FAQ already refuses a published timeline; this page exists so you can still add, without us pretending the defaults are data.
What each input means
Inputs on this tool, in the order they appear on the form.
Input
What it is actually asking
Design
Architecture, engineering, survey, energy documents, revisions after the first city comments. Longer if you have not settled use and form.
Permit review
Planning or zoning plus building permit, including back-checks. Ask the city. Do not type a number from a different metro.
Site / foundation
Demo, grading, utilities in the ground, the pad. Weather and access sit here.
Building
Stick-built weeks on site, or factory lead plus set and stitch. Two different calendars; type the one that applies.
Finishes / CO
Interior, final inspections, utility meters live, certificate of occupancy. A kitchen lead time lives here if it was not in building.
Worked examples
Including one where the naive answer misleads, which is the example most calculators leave out.
The editorial defaults, unmodified
8 + 12 + 4 + 16 + 4 = 44 weeks if nothing overlaps and nothing waits on the city longer than 12. Longest line: building at 16, unless you raise review. This is a planning sketch. Overwrite it the moment someone who has permitted an ADU in your city gives you different weeks.
A conversion with a slow counter
Design 6, review 24, site 2, building 10, finishes 3 = 45 weeks. The conversion is “faster on site” and the project is not faster, because review ate half a year. That is the point of keeping review as its own line.
The one where “ADUs take four months” misleads
Four months is sometimes the on-site construction of a modular set, photographed without the year of drawings and comments that preceded the crane. Summing only building and finishes is the naive answer.
This tool will still let you type that, and the permit line will sit there at 12 (or whatever you left) as the part of the story the photo omitted.
What changes the result
Review weeks move the total one-for-one in this model. They also tend to be the weeks that slip. Completeness of the set is the one thing you control: missing energy calcs and unsigned structural sheets are how 12 becomes 20.
Building weeks drop for conversions and some factory routes. If you cut building and do not ask the factory its queue, you have moved the wait off the form, not off the calendar.
A second bathroom, a soil report, or a septic redesign belongs in the line that actually waits on it. Hiding it in contingency weeks is how schedules die politely.
Local considerations
Review times are a staffing fact at a named counter. They change. We will not publish a city table we have not measured. Call planning and ask for current ADU review times, in weeks, for a complete set. Then type that number.
When not to use this
Do not put the default 44 weeks in a contract. Do not use this as a liquidated-damages schedule. Do not start the design clock before feasibility.
HyreADU does not schedule crews and does not know your city’s backlog.
Related on this site
The usual sequenceSix phases on the homepage. Feasibility is first and free.
The six ADU formsPrefab vs site-built vs conversion. Relative time on site, no week counts.
Questions this calculator answers
How long does it take to build an ADU?
We do not publish a national figure. The schedule is dominated by planning and permit review in your jurisdiction, utility scheduling, and construction method. Modular and prefab shorten on-site construction, not review. Permitting is frequently the longest single phase, it is the one you control least, and it begins after design.
What are the defaults on this form?
Editorial planning placeholders: 8 weeks design, 12 weeks review, 4 weeks site, 16 weeks building, 4 weeks finishes. They are not a survey, not your city, and not a promise. Change them.
Can phases overlap?
Some site work can overlap late design details. Inspections cannot overlap with hope. This tool sums, which is conservative. If your builder has a real Gantt with overlaps, use that and treat this as a sanity check.
Why is permit review singled out?
Because you do not control it. Staffing, completeness of the set, design review and back-checks move it. A 12-week placeholder is not a service-level agreement.
Does prefab save time?
On site, often. The factory has its own queue. Crane day still needs a foundation and a permit. The comparison table on the homepage is relative: factory routes spend less time as a hole in the yard. Review is still review.
What about utility scheduling?
A meter, a tap or a septic redesign can sit outside both the builder’s schedule and the city’s. Put it in site or in finishes if that is when it actually happens, or add weeks to whichever line is waiting on it.
When should I start design?
After a conversation with planning, not before. Paying for drawings of a building the zone will not hold is the failure mode the feasibility checker exists to prevent.
Do inspections add weeks?
Failed inspections do. Passing ones are already inside a competent building-phase number. Ask the builder how many inspections they expect and what happens when one fails.
Is winter a factor?
Foundation and some exterior trades stop or slow in cold climates. That is local. Add weeks to site and building if you are opening the ground in January in a frost belt. We will not invent a climate table.
Does HyreADU schedule projects?
No. This is arithmetic on weeks you typed. Matching is still being built.
Sources and methodology
Figures dated 26 August 2026. Last reviewed .
LADBS Building and Safety — Building Permits Issued from 2020 to Present (N) (Los Angeles, retrieved 2026-09-05. HyreADU analysis of issued ADU building permits: n=27,188, median 162.0 calendar days from application to issuance (IQR 79.0-301.0). Measures a different span from the statutory decision clock.)
DataSF Building Permits (DBI Permit Tracking System extract) (San Francisco, retrieved 2026-09-05. HyreADU analysis of issued ADU building permits: n=1,713, median 445 calendar days from application to issuance (IQR 276-707). Measures a different span from the statutory decision clock.)
Marin County Community Development Agency — Building Permit (mkbn-caye) (Marin County (unincorporated), retrieved 2026-09-05. HyreADU analysis of issued ADU building permits: n=472, median 174.5 calendar days from application to issuance (IQR 105.0-308.2). Measures a different span from the statutory decision clock.)
Adopted state and local building codes (International Code Council, retrieved 2026-08-26. Inspections follow the adopted code. Their calendar is local staffing, not the model code.)
Accessory dwelling unit research (HUD User, retrieved 2026-08-26. Cited for ADUs as a process with design, review and construction, not as a week count.)