ADU construction time statistics

34 of 47 figures are HyreADU calculations. Permit issuance to certificate of occupancy, estimated so that the 14,306 permits which have not finished stay inside the calculation instead of being quietly dropped.

Updated September 2026 · Data as of LADBS resource pi9x-tg5x retrieved 2026-09-05; feed rowsUpdatedAt 2026-08-31; observation window closes 2026-08-31; HCD APR Table A2 retrieved 2026-09-05

Written by HyreADU Research Desk Primary-source research and data analysis

Audited by HyreADU Research Desk Provenance and figure-ledger audit

499 days median, permit issued to certificate of occupancy About 16.4 months. Kaplan-Meier estimate, n = 39,278 permits with 24,972 completions observed, IQR 292–1066 days. City of Los Angeles.
35.3% reach a certificate of occupancy within one year 65.1% within two years, 75.5% within three. The "three to six months" claim is not visible anywhere in this distribution.
15.3% of 2020-issued ADU permits still have no final 517 of 3,373 permits, 6.2 years after issuance. HyreADU calculation on LADBS pi9x-tg5x.

The short version

On 39,278 non-supplemental City of Los Angeles building permits that add an accessory dwelling unit, the estimated median time from permit issuance to certificate of occupancy is 499 days — about 16.4 months — with an interquartile range of 292–1066 days.

That figure keeps the unfinished permits in it, and that is the whole point. 14,306 of the 39,278 permits in the frame have no completion event yet.

Take the median of the 24,972 that finished and you get 367 days — 132 days shorter, roughly four months.

The shorter number is the one a builder’s own records would produce, and it is wrong in a specific direction: it can only see the projects that ended.

Only 35.3% of issued ADU permits reach a certificate of occupancy within a year, 65.1% within two and 75.5% within three.

What you build changes the clock more than anything else observable. A detached new build runs a median 564 days; an attached addition 528 days; a conversion coded as an alteration 419 days.

A junior ADU — a unit made inside an existing bedroom footprint — is fastest at 387 days.

And a substantial minority never finish on paper at all. 15.3% of the ADU permits Los Angeles issued in 2020 still have no certificate and no permit final, 6.2 years on; for the 2022 cohort it is 21.0%.

A statewide instrument agrees on the shape. Across California, among 81,853 matched projects HCD’s median permit-to-certificate lag is 1 year, with 78.9% inside one year and 93.9% inside two — and the 2018 permit cohort’s observed completion rate is 47.1% after seven years.

This is Los Angeles, not California and not the United States. It is not a compliance finding, not a construction schedule and not advice. 34 of 47 figures below are HyreADU calculations (34 hyreadu calculation, 12 agency published, 1 trade / survey estimate).

Read this before you use the number

Five constraints. The first is a statistical point that changes the headline by four months, so it is not optional.

  • Unfinished permits have to stay in the calculation

    14,306 of 39,278 permits in this frame have not reached a certificate. Dropping them and taking the median of the 24,972 that finished gives 367 days instead of 499 days.

    That is not a rounding difference; it is a systematic bias, because the projects that take longest are precisely the ones most likely to be unfinished on the day you look.

    Every headline figure here is a Kaplan-Meier product-limit estimate, which keeps a permit in the denominator until the day it drops out of observation. The completed-only figure is printed beside it every time.

  • This is one city, and it is not California

    Los Angeles is the only jurisdiction this desk has found that publishes an issuance date and a certificate-of-occupancy date on the same permit row.

    San Francisco, Sacramento, San José, unincorporated Marin and San Diego were all opened; none of their published extracts carries a usable completion date paired to an ADU flag. So the frame is the City of Los Angeles.

    A statewide instrument is set alongside it below, at much coarser resolution.

  • A certificate is a paperwork event, not a move-in date

    The clock stops when the department records a certificate of occupancy (24,876 cases) or a permit final (96).

    Some units are occupied before that record exists and some sit finished for months while a last inspection is chased.

    Equally, a permit with no final is not necessarily an empty building site — it can be a finished ADU whose owner never closed the permit out.

  • This clock starts at issuance, not at the beginning of the project

    Everything before the permit — design, plan check, corrections, fees — is the other clock, and in Los Angeles its median is 162 days.

    Adding the two medians gives 661 days, about 1.8 years, and that sum is a HyreADU cross-study calculation offered as an order of magnitude. It is not a measured end-to-end duration on the same permits.

  • None of this is a schedule for your project

    The interquartile range here is wider than the median. That means the middle half of ADU projects in one city have experiences that differ by more than two years. Use these figures to sanity-check a timeline someone has given you, not to build one. HyreADU does not design, permit or build accessory dwelling units.

Why the honest number is four months longer than the builder number

Median days from ADU permit issuance to certificate of occupancy, by permit issue year0114227341455568202020212022202320242025Median calendar daysYear the permit was issuedCensored-aware (Kaplan-Meier)Finished permits onlyThe gap between the two lines widens in recent cohorts because more of those permits are still open. Same numbers as the by-yeartable.
The two medians by permit issue year: censored-aware against finished-permits-only. HyreADU calculation on LADBS resource pi9x-tg5x, retrieved 2026-09-05.

Imagine standing in the middle of a marathon course with a stopwatch and recording the finishing times of everyone who has already crossed the line.

Your average will be excellent, and it will be wrong, because the runners still on the course are exactly the slow ones.

That is what happens to every ADU build-time figure computed from completed projects.

In this frame the effect is large and measurable. Across all 39,278 permits, the censored-aware median is 499 days.

Across only the 24,972 that finished, it is 367 days — 132 days, roughly four months, shorter.

The mean on finished permits is 446 days, which is closer but is a mean, and means on right-skewed distributions describe nobody.

The bias gets worse the more recent the cohort, which is visible in the chart above: the two lines are close for 2020-issued permits, where most projects have had time to finish either way, and far apart for 2025-issued permits, where the completed-only median of 258 days is a statement about the unusually fast minority that has already closed out. A trade figure sourced from recent projects is therefore doubly optimistic.

Kaplan-Meier is the standard tool for this and it is not exotic — it is the same estimator used for survival curves in medicine.

It keeps every permit in the denominator until the day it either completes or leaves observation, so a permit issued in 2025 contributes evidence about the first fourteen months and then stops contributing rather than being counted as either fast or infinite.

The full method, including the four sensitivity frames, is on the construction-duration study.

When permits actually finish

The median is one point on a curve, and for anyone planning around this the curve is more useful. These are the cumulative shares reaching a certificate of occupancy at four horizons.

When a Los Angeles ADU permit reaches a certificate of occupancy35.3%Certificate within 1 year — 353 per thousand permits29.8%Between 1 and 2 years — 298 per thousand permits10.4%Between 2 and 3 years — 104 per thousand permits24.5%Beyond 3 years or not yet — 245 per thousand permitsKaplan-Meier estimates on n = 39,278 permits with 24,972 observed completions. Same numbers as the milestone table.
Of every thousand Los Angeles ADU permits, when a certificate of occupancy arrives. Kaplan-Meier estimates on LADBS pi9x-tg5x, n = 39,278, retrieved 2026-09-05.
Horizon after permit issuanceShare reaching a certificateRemainingClass
Within 1 year35.3%64.7%HyreADU calculation
Within 18 months54.3%45.7%HyreADU calculation
Within 2 years65.1%34.9%HyreADU calculation
Within 3 years75.5%24.5%HyreADU calculation

HyreADU calculation on LADBS pi9x-tg5x, retrieved 2026-09-05, observation window closing 2026-08-31. Kaplan-Meier product-limit estimates on n = 39,278 permits with 24,972 observed completion events.

Read the last row carefully. Roughly a quarter of issued Los Angeles ADU permits have not produced a certificate of occupancy three years after issuance. That is the number that should be in any risk conversation about an ADU project, and it is almost never the number in a brochure.

By what is actually being built

The permit type is the closest thing in this data to a construction method, and it moves the median by 145 days between the extremes — more than any other cut on this page.

A new-construction permit is a detached unit with a foundation, a new service and a full structural review. An alteration permit is usually a garage or interior conversion.

A junior ADU is a unit created inside an existing bedroom footprint, and it is the fastest thing in the dataset.

Median issuance-to-certificate days by what the permit describes0New construction (detached ADU)564 daysAddition (attached ADU)528 daysAlteration/repair (conversion)419 daysJunior ADU387 daysStandard ADU509 daysKaplan-Meier medians. Same numbers as the type table.
Median issuance-to-certificate days by permit type and by junior-ADU flag. HyreADU calculation on LADBS pi9x-tg5x, retrieved 2026-09-05.
What the permit describesMedianIQRWithin 1 yearWithin 2 yearsnCompleted-only medianClass
New construction (detached ADU)564 days365–1058 days25.0%62.5%10,612439 daysHyreADU calculation
Addition (attached ADU)528 days325–1121 days31.0%63.3%12,227393 daysHyreADU calculation
Alteration/repair (conversion)419 days230–999 days44.6%68.2%16,438304 daysHyreADU calculation
Junior ADU (JADU)387 days212–908 days47.3%70.3%3,778—HyreADU calculation
Standard ADU509 days301–1086 days34.0%64.5%35,500—HyreADU calculation

HyreADU calculation on LADBS pi9x-tg5x, retrieved 2026-09-05. Kaplan-Meier medians; the last column shows what each row would look like if unfinished permits were dropped, which is between four and five months shorter in every case.

The ordering is intuitive and the size of the gap is not.

A conversion finishes 145 days sooner than a detached new build at the median, and 19.6% more of them are done inside a year.

See the garage-conversion page on what a garage conversion actually involves, and the junior-ADU page on why junior units behave differently from everything else here.

By the year the permit was issued

Each row is a permit cohort followed forward. Recent cohorts have had less time to complete, so their censored-aware medians are estimates over a shorter observation window and their completed-only medians are severely biased — both are printed so the difference is visible.

Permit issue yearIssuedCompleted so farCensored-aware medianCompleted-only medianWithin 1 yearClass
20203,3732,856486 days395 days39.1%HyreADU calculation
20215,0714,174508 days427 days33.0%HyreADU calculation
20227,1205,625536 days429 days31.6%HyreADU calculation
20236,1584,674512 days394 days34.2%HyreADU calculation
20246,3944,384476 days342 days37.7%HyreADU calculation
20256,9333,045462 days258 days37.9%HyreADU calculation
20264,2292140 days126 days16.4%HyreADU calculation

HyreADU calculation on LADBS pi9x-tg5x, retrieved 2026-09-05. 2026 is a part year. The completed-only column falls sharply in recent years for a reason that has nothing to do with faster building: in a young cohort, the only permits that have finished are the fast ones.

The censored-aware medians are broadly stable across cohorts — 486 days for 2020, 536 days for 2022, 476 days for 2024 — which is the more honest reading than the completed-only column’s apparent collapse from 395 days to 258 days.

The permits that never close out

Permits that never close out are the finding the study did not expect, and they are separate from the duration question. These four cohorts are mature enough that a normal project would have finished. A meaningful share of them has no certificate of occupancy and no permit final at all.

Share of issued Los Angeles ADU permits reaching a certificate of occupancy within one year35.3% within one year — each square is one permit in a thousandKaplan-Meier, n = 39,278
35.3% of issued Los Angeles ADU permits reach a certificate of occupancy within one year. Kaplan-Meier estimate on LADBS pi9x-tg5x, n = 39,278, retrieved 2026-09-05.
2020 cohort15.3%
517 of 3,373 permits · 6.2 years elapsed
2021 cohort17.7%
897 of 5,071 permits · 5.2 years elapsed
2022 cohort21.0%
1,495 of 7,120 permits · 4.2 years elapsed
2023 cohort24.1%
1,484 of 6,158 permits · 3.2 years elapsed
Permit issue yearIssuedCompletedNo finalShare with no finalYears elapsedClass
20203,3732,85651715.3%6.2HyreADU calculation
20215,0714,17489717.7%5.2HyreADU calculation
20227,1205,6251,49521.0%4.2HyreADU calculation
20236,1584,6741,48424.1%3.2HyreADU calculation

HyreADU calculation on LADBS pi9x-tg5x, retrieved 2026-09-05, observation window closing 2026-08-31. Years elapsed are measured from the midpoint of the issue year.

Of the 14,306 open permits across all years, 12,735 remain in "Issued" status, 701 are marked "CofO in Progress" and 304 have expired.

These are not all abandoned projects — some are finished units whose owners never closed the permit — but they are the permit-to-completion gap made visible at the level of the individual project, which is exactly what the statewide HCD figures cannot show.

The builder-attrition study looks at the builder side of the same gap.

By area of the city

Seven area planning commissions, one building department, one code. The spread between the fastest and slowest medians is 121 days — real, but much smaller than the spread by ADU type, which is the useful comparison to keep in mind.

Area planning commissionMedianIQRWithin 1 yearWithin 2 yearsnClass
South Valley464 days277–1014 days38.2%67.0%11,379HyreADU calculation
North Valley467 days273–975 days38.4%67.5%9,764HyreADU calculation
South Los Angeles551 days321–1258 days31.0%61.0%6,297HyreADU calculation
West Los Angeles504 days301–1001 days34.2%65.8%4,196HyreADU calculation
East Los Angeles527 days305–1070 days33.0%64.6%3,346HyreADU calculation
Central585 days334–1370 days28.7%59.0%3,274HyreADU calculation
Harbor529 days314–977 days32.3%65.2%1,022HyreADU calculation

HyreADU calculation on LADBS pi9x-tg5x, retrieved 2026-09-05. The two San Fernando Valley commissions — South Valley and North Valley — carry 53.8% of the city’s ADU permits between them and are also the two fastest.

Do not read this as a map of departmental performance. Area correlates with lot size, lot slope, the age and construction type of the existing house, the prevalence of garage conversions, and the mix of owner-builder against contractor work. It is a description of where the slower projects are, not an explanation of why.

The statewide check: HCD’s permit-to-certificate lag

A second instrument, at coarser resolution, across all of California. HCD’s Table A2 records both a permit and a completion for a project, so a lag can be measured in whole calendar years across 81,853 matched projects statewide.

It cannot see days, and it can only see projects whose completion was reported under the same identifier — but it is not one city.

Lag from permit year to completion yearMatched projectsShareClass
Same calendar year24,07729.4%HyreADU calculation
One year later40,48649.5%HyreADU calculation
Two years later12,26415.0%HyreADU calculation
Three years or more4,9746.1%HyreADU calculation
Negative (reporting artefact)520.1%HyreADU calculation

HyreADU calculation on HCD APR Table A2, retrieved 2026-09-05. Median lag 1 year; 78.9% of matched projects complete within one year and 93.9% within two. 52 projects show a completion dated before the permit, which is a reporting artefact rather than a finding.

Two cautions. First, calendar-year lag is coarser than it sounds: a permit issued in December and a certificate issued the following February is a one-year lag here and ten weeks in reality.

Second, this table only contains projects that matched — statewide, 40.9% of 2018–2023 permit units have no matching completion row at all, and those are disproportionately the slow and the stalled. Both instruments therefore describe the finishing projects better than the stuck ones. See the permits-vs-completions study.

How the headline moves under different definitions of "an ADU permit"

One dataset, four defensible ways to decide which rows are ADU permits. The headline frame uses the department’s net-unit change and junior-ADU flag with supplementals excluded. The other three are printed so you can see that the finding does not depend on that choice.

FramenCompletions observedMedianIQRClass
Headline: permit adds a net ADU or JADU (adu_changed > 0 or junior_adu = 1), supplementals excluded39,27824,972499 days292–1066 daysHyreADU calculation
Department use classification only (use_desc contains “Accessory Dwelling”), supplementals excluded — the ADU-04 classifier25,97916,660506 days301–1071 daysHyreADU calculation
Both classifiers must agree25,36016,267508 days304–1071 daysHyreADU calculation
Headline classifier, supplemental permits left in41,35926,618485 days280–1025 daysHyreADU calculation

HyreADU calculation on LADBS pi9x-tg5x, retrieved 2026-09-05. The four frames span 485 to 508 days at the median — a range of 23 days, which is small next to the 132-day difference the censoring correction makes.

That comparison is the point of the table. Which rows you call ADU permits barely moves the answer. Whether you keep unfinished permits in the calculation moves it by four months.

Every figure on this page, with its class

47 figures with geography, date, provenance class and source. 34 HyreADU calculations, 12 agency-published, 1 trade or survey.

StatisticFigureGeographyDateClassSource
Permit rows downloaded from the department feed409,619City of Los Angeles2020–2026Agency publishedLADBS resource pi9x-tg5x, retrieved 2026-09-05 (rowsUpdatedAt 2026-08-31, observation window closes 2026-08-31)
Rows carrying the department’s ADU or JADU flag41,374City of Los Angeles2020–2026Agency publishedLADBS resource pi9x-tg5x, retrieved 2026-09-05 (rowsUpdatedAt 2026-08-31, observation window closes 2026-08-31)
Supplemental permits excluded from the frame2,095City of Los Angeles2020–2026Agency publishedLADBS resource pi9x-tg5x, retrieved 2026-09-05 (rowsUpdatedAt 2026-08-31, observation window closes 2026-08-31)
Permits in the analysis frame39,278City of Los Angeles2020–2026Agency publishedLADBS resource pi9x-tg5x, retrieved 2026-09-05 (rowsUpdatedAt 2026-08-31, observation window closes 2026-08-31)
Permits with a completion event observed24,972City of Los Angeles2020–2026Agency publishedLADBS resource pi9x-tg5x, retrieved 2026-09-05 (rowsUpdatedAt 2026-08-31, observation window closes 2026-08-31)
Permits with no completion event observed14,306City of Los Angeles2020–2026Agency publishedLADBS resource pi9x-tg5x, retrieved 2026-09-05 (rowsUpdatedAt 2026-08-31, observation window closes 2026-08-31)
Completions recorded via a certificate of occupancy24,876City of Los Angeles2020–2026Agency publishedLADBS resource pi9x-tg5x, retrieved 2026-09-05 (rowsUpdatedAt 2026-08-31, observation window closes 2026-08-31)
Completions recorded via a permit final rather than a certificate96City of Los Angeles2020–2026Agency publishedLADBS resource pi9x-tg5x, retrieved 2026-09-05 (rowsUpdatedAt 2026-08-31, observation window closes 2026-08-31)
Open permits still in “Issued” status12,735City of Los Angelesas of 2026-08-31Agency publishedLADBS resource pi9x-tg5x, retrieved 2026-09-05 (rowsUpdatedAt 2026-08-31, observation window closes 2026-08-31)
Open permits marked expired304City of Los Angelesas of 2026-08-31Agency publishedLADBS resource pi9x-tg5x, retrieved 2026-09-05 (rowsUpdatedAt 2026-08-31, observation window closes 2026-08-31)
ADU certificates of occupancy reported statewide102,356California, 511 reporting jurisdictions2018–2025Agency publishedHCD Housing Element APR, Table A2, retrieved 2026-09-05
Matched permit-to-certificate project pairs statewide81,853California, 511 reporting jurisdictions2018–2025Agency publishedHCD Housing Element APR, Table A2, retrieved 2026-09-05
Median days, permit issuance to certificate of occupancy499 daysCity of Los Angeles2020–2026HyreADU calculationLADBS resource pi9x-tg5x, retrieved 2026-09-05 (rowsUpdatedAt 2026-08-31, observation window closes 2026-08-31) · construction-duration study
Same median expressed in months16.4 monthsCity of Los Angeles2020–2026HyreADU calculationLADBS resource pi9x-tg5x, retrieved 2026-09-05 (rowsUpdatedAt 2026-08-31, observation window closes 2026-08-31) · construction-duration study
Interquartile range, issuance to certificate292–1066 daysCity of Los Angeles2020–2026HyreADU calculationLADBS resource pi9x-tg5x, retrieved 2026-09-05 (rowsUpdatedAt 2026-08-31, observation window closes 2026-08-31) · construction-duration study
Median computed on finished permits only367 daysCity of Los Angeles2020–2026HyreADU calculationLADBS resource pi9x-tg5x, retrieved 2026-09-05 (rowsUpdatedAt 2026-08-31, observation window closes 2026-08-31) · construction-duration study
Understatement produced by ignoring unfinished permits132 daysCity of Los Angeles2020–2026HyreADU calculationLADBS resource pi9x-tg5x, retrieved 2026-09-05 (rowsUpdatedAt 2026-08-31, observation window closes 2026-08-31) · construction-duration study
Mean on finished permits only, for contrast446 daysCity of Los Angeles2020–2026HyreADU calculationLADBS resource pi9x-tg5x, retrieved 2026-09-05 (rowsUpdatedAt 2026-08-31, observation window closes 2026-08-31) · construction-duration study
Share reaching a certificate within one year35.3%City of Los Angeles2020–2026HyreADU calculationLADBS resource pi9x-tg5x, retrieved 2026-09-05 (rowsUpdatedAt 2026-08-31, observation window closes 2026-08-31) · construction-duration study
Share reaching a certificate within eighteen months54.3%City of Los Angeles2020–2026HyreADU calculationLADBS resource pi9x-tg5x, retrieved 2026-09-05 (rowsUpdatedAt 2026-08-31, observation window closes 2026-08-31) · construction-duration study
Share reaching a certificate within two years65.1%City of Los Angeles2020–2026HyreADU calculationLADBS resource pi9x-tg5x, retrieved 2026-09-05 (rowsUpdatedAt 2026-08-31, observation window closes 2026-08-31) · construction-duration study
Share reaching a certificate within three years75.5%City of Los Angeles2020–2026HyreADU calculationLADBS resource pi9x-tg5x, retrieved 2026-09-05 (rowsUpdatedAt 2026-08-31, observation window closes 2026-08-31) · construction-duration study
Median, new construction (detached ADU)564 daysCity of Los Angeles2020–2026HyreADU calculationLADBS resource pi9x-tg5x, retrieved 2026-09-05 (rowsUpdatedAt 2026-08-31, observation window closes 2026-08-31) · construction-duration study
Median, addition (attached ADU)528 daysCity of Los Angeles2020–2026HyreADU calculationLADBS resource pi9x-tg5x, retrieved 2026-09-05 (rowsUpdatedAt 2026-08-31, observation window closes 2026-08-31) · construction-duration study
Median, alteration or repair (conversion)419 daysCity of Los Angeles2020–2026HyreADU calculationLADBS resource pi9x-tg5x, retrieved 2026-09-05 (rowsUpdatedAt 2026-08-31, observation window closes 2026-08-31) · construction-duration study
Gap between a detached new build and a conversion145 daysCity of Los Angeles2020–2026HyreADU calculationLADBS resource pi9x-tg5x, retrieved 2026-09-05 (rowsUpdatedAt 2026-08-31, observation window closes 2026-08-31) · construction-duration study
Median, junior ADU387 daysCity of Los Angeles2020–2026HyreADU calculationLADBS resource pi9x-tg5x, retrieved 2026-09-05 (rowsUpdatedAt 2026-08-31, observation window closes 2026-08-31) · construction-duration study
Median, standard ADU509 daysCity of Los Angeles2020–2026HyreADU calculationLADBS resource pi9x-tg5x, retrieved 2026-09-05 (rowsUpdatedAt 2026-08-31, observation window closes 2026-08-31) · construction-duration study
Share of junior ADUs finished within a year47.3%City of Los Angeles2020–2026HyreADU calculationLADBS resource pi9x-tg5x, retrieved 2026-09-05 (rowsUpdatedAt 2026-08-31, observation window closes 2026-08-31) · construction-duration study
Slowest area planning commission by medianCentral, 585 daysCity of Los Angeles2020–2026HyreADU calculationLADBS resource pi9x-tg5x, retrieved 2026-09-05 (rowsUpdatedAt 2026-08-31, observation window closes 2026-08-31) · construction-duration study
Fastest area planning commission by medianSouth Valley, 464 daysCity of Los Angeles2020–2026HyreADU calculationLADBS resource pi9x-tg5x, retrieved 2026-09-05 (rowsUpdatedAt 2026-08-31, observation window closes 2026-08-31) · construction-duration study
Spread between fastest and slowest area121 daysCity of Los Angeles2020–2026HyreADU calculationLADBS resource pi9x-tg5x, retrieved 2026-09-05 (rowsUpdatedAt 2026-08-31, observation window closes 2026-08-31) · construction-duration study
2020-issued permits with no final15.3% (517 of 3,373)City of Los Angeles2020 cohortHyreADU calculationLADBS resource pi9x-tg5x, retrieved 2026-09-05 (rowsUpdatedAt 2026-08-31, observation window closes 2026-08-31) · construction-duration study
2021-issued permits with no final17.7%City of Los Angeles2021 cohortHyreADU calculationLADBS resource pi9x-tg5x, retrieved 2026-09-05 (rowsUpdatedAt 2026-08-31, observation window closes 2026-08-31) · construction-duration study
2022-issued permits with no final21.0%City of Los Angeles2022 cohortHyreADU calculationLADBS resource pi9x-tg5x, retrieved 2026-09-05 (rowsUpdatedAt 2026-08-31, observation window closes 2026-08-31) · construction-duration study
2023-issued permits with no final24.1%City of Los Angeles2023 cohortHyreADU calculationLADBS resource pi9x-tg5x, retrieved 2026-09-05 (rowsUpdatedAt 2026-08-31, observation window closes 2026-08-31) · construction-duration study
Median under the department-classification sensitivity frame506 daysCity of Los Angeles2020–2026HyreADU calculationLADBS resource pi9x-tg5x, retrieved 2026-09-05 (rowsUpdatedAt 2026-08-31, observation window closes 2026-08-31) · construction-duration study
Median when both classifiers must agree508 daysCity of Los Angeles2020–2026HyreADU calculationLADBS resource pi9x-tg5x, retrieved 2026-09-05 (rowsUpdatedAt 2026-08-31, observation window closes 2026-08-31) · construction-duration study
Median with supplemental permits left in485 daysCity of Los Angeles2020–2026HyreADU calculationLADBS resource pi9x-tg5x, retrieved 2026-09-05 (rowsUpdatedAt 2026-08-31, observation window closes 2026-08-31) · construction-duration study
Statewide median permit-to-certificate lag among matched projects1 yearCalifornia, 511 reporting jurisdictions2018–2025HyreADU calculationHCD Housing Element APR, Table A2, retrieved 2026-09-05 · permits-vs-completions study
Matched projects completing in the permit year29.4%California, 511 reporting jurisdictions2018–2025HyreADU calculationHCD Housing Element APR, Table A2, retrieved 2026-09-05 · permits-vs-completions study
Matched projects completing within one year78.9%California, 511 reporting jurisdictions2018–2025HyreADU calculationHCD Housing Element APR, Table A2, retrieved 2026-09-05 · permits-vs-completions study
Matched projects completing within two years93.9%California, 511 reporting jurisdictions2018–2025HyreADU calculationHCD Housing Element APR, Table A2, retrieved 2026-09-05 · permits-vs-completions study
Matched projects taking three years or more4,974California, 511 reporting jurisdictions2018–2025HyreADU calculationHCD Housing Element APR, Table A2, retrieved 2026-09-05 · permits-vs-completions study
2018 permit cohort, observed completion rate after seven years47.1%California, 511 reporting jurisdictions2018 cohortHyreADU calculationHCD Housing Element APR, Table A2, retrieved 2026-09-05 · permits-vs-completions study
Combined median of both clocks, application to certificate661 daysCity of Los Angeles2020–2026HyreADU calculationLADBS resource pi9x-tg5x, retrieved 2026-09-05 (rowsUpdatedAt 2026-08-31, observation window closes 2026-08-31) · permit-times study + construction-duration study
New California ADUs that are one-bedroom61%California, 2018–19 owner surveyApr 2021Trade / survey estimateChapple, Ganetsos and Lopez, CCI, 22 April 2021

HyreADU calculation — computed by HyreADU, method on the construction-duration study. Agency published — a frame count printed by the department or by HCD. Trade / survey estimate — a named survey. LADBS extract retrieved 2026-09-05, observation window closing 2026-08-31.

Build-time claims we will not repeat

  • “An ADU takes three to six months to build”

    On 39,278 Los Angeles permits, 35.3% reach a certificate within a year.

    Three to six months is not the median, not the first quartile (292 days is over nine months) and not a horizon at which any meaningful share of this distribution has finished.

    The claim is roughly what you get from the completed-only median of 367 days with further optimism applied, and it survives because the people quoting it never see the permits that stalled.

  • A national or statewide ADU build time

    Exactly one jurisdiction in the country, as far as this desk can establish, publishes an issuance date and a completion date on the same ADU permit row.

    Any figure presented as a national ADU construction time is either a trade estimate or an extrapolation from somewhere it was not measured.

    HCD’s statewide lag is real but is measured in whole calendar years and only over matched projects.

  • A build time computed from finished projects only

    This is the single most common methodological error in the category and it is worth 132 days.

    A builder reporting "our average ADU takes fourteen months" is reporting the truth about their finished jobs and saying nothing about the ones still open.

    The correction is not a matter of opinion — it is the difference between 367 days and 499 days on the same permits.

  • A permit-with-no-final read as an abandoned project

    15.3% of 2020-issued permits have no final. That set includes genuinely stalled projects, and it also includes finished ADUs whose owners never chased the last inspection, projects re-permitted under a new number, and units sold mid-build.

    We publish the share and name what it contains. Converting it into an abandonment rate would be a fabrication with a real number attached.

Citing these figures

Cite the construction-duration study rather than this digest where you can — the estimator, the four sensitivity frames and the completion-path definitions live there.

For anything labeled HyreADU calculation from the Los Angeles data, attribute it as "HyreADU analysis of City of Los Angeles building permits (Socrata pi9x-tg5x), retrieved 2026-09-05, Kaplan-Meier estimate".

For the statewide lag, attribute it as "HyreADU analysis of the California HCD Housing Element Annual Progress Report, Table A2". Corrections go on the page with a dated note: hello@hyreadu.com.

If you are quoting a single figure and have room for only one qualification, make it this one: 499 days, City of Los Angeles, censored-aware. Dropping either the city or the estimator turns a careful measurement into a misleading one.

Questions

How long does it take to build an ADU?
From building-permit issuance to certificate of occupancy in the City of Los Angeles, the median is 499 days — about 16.4 months — with an interquartile range of 292–1066 days. That is a Kaplan-Meier estimate over 39,278 permits which keeps the 14,306 unfinished permits in the calculation. Only 35.3% reach a certificate within a year.
Why is your figure so much longer than what builders quote?
Because builders compute it from finished jobs. Take the median of only the 24,972 permits in this frame that have completed and you get 367 days — 132 days shorter. That calculation cannot see the projects that are still open after three years, and those are exactly the slow ones. It is the same bias as timing a marathon by stopping the clock at the halfway point and averaging whoever has already finished.
Does a garage conversion go faster than a detached new build?
Yes, substantially. A permit coded as an alteration or repair — mostly conversions — has a median of 419 days from issuance to certificate, with 44.6% finished inside a year. A new-construction detached ADU runs 564 days, with 25.0% inside a year. An attached addition sits between them at 528 days. Junior ADUs are fastest of all at 387 days.
What share of ADU projects finish within a year?
35.3% in Los Angeles. 54.3% within eighteen months, 65.1% within two years and 75.5% within three. Roughly a quarter of issued ADU permits have produced no certificate of occupancy three years after issuance.
What happens to the permits that never get a certificate?
We do not know, and we will not guess. 15.3% of the ADU permits Los Angeles issued in 2020 have no certificate and no permit final 6.2 years later, rising to 24.1% for the 2023 cohort. Of all 14,306 open permits, 12,735 sit in "Issued" status and 304 have expired. That set will contain stalled and abandoned projects, and it will also contain finished ADUs whose owners never closed the permit out. Calling the whole share an abandonment rate would be wrong.
Is this a California figure or a national one?
Neither. It is the City of Los Angeles, which is the only jurisdiction this desk has found that publishes a permit-issuance date and a certificate date on the same ADU permit row. A coarser statewide check is available from HCD: among matched California projects the median permit-to-certificate lag is one calendar year, with 78.9% completing within one year and 93.9% within two. There is no national ADU construction-time series and nothing here is scaled into one.
How long is the whole process, from first application to keys?
Adding the two Los Angeles medians — 162 days from application to permit issuance, 499 days from issuance to certificate — gives 661 days, about 1.8 years. That sum is a HyreADU cross-study calculation and an order of magnitude, not a measured end-to-end duration: the two clocks are computed on overlapping but not identical permit sets, and a single project’s two segments are not necessarily both at the median. Treat it as the right scale rather than a schedule.
Does where in the city you build change the build time?
A little. Across the seven Los Angeles area planning commissions the medians run from 464 days in South Valley to 585 days in Central, a spread of 121 days. That is real but much smaller than the 145-day spread between a conversion and a detached new build, and area correlates with lot size, slope, house age and project mix rather than with departmental speed.
Does the finding depend on how you defined an "ADU permit"?
No, and that was checked deliberately. Four different classification frames — the department’s net-unit change, its use description, both agreeing, and supplementals left in — give medians of 499, 506, 508, 485 days. The spread across all four is 23 days, against the 132-day effect of the censoring correction. The classification choice is a rounding error; the estimator choice is the finding.
How current is this and when will it change?
The LADBS feed was retrieved 2026-09-05 with rowsUpdatedAt 2026-08-31, and the observation window closes 2026-08-31. The feed refreshes daily, so cohort completion shares move continuously; the medians move slowly. We re-cut the page rather than editing figures in place, and note the change here.

Written and audited by

HyreADU Research Desk

Primary-source research, data analysis and fact checking

We are a research desk, not a builder. We read the permit extract, the statute, the HCD return or the fee schedule ourselves, and publish each figure with its source and retrieval date.

Where a number cannot be traced to a primary source, we leave it out and say what we could not verify. Our store-based claims cover California only.

CA
the only state this desk will make store-based claims about
5
jurisdictions with extracted ADU permit evidence
735
CSLB-verified companies in the California store
0
national claims from a one-state store

How this desk works

  • Primary sources only. Permit counts come from the city or county that issued the permit. Production counts come from HCD’s Annual Progress Report. Rents come from HUD or the Census. We do not cite an article that cites a source; we download the source and compute the figure ourselves.
  • This is a California site. The company store is 734 California firms and one New Mexico firm. Permit evidence exists for five named jurisdictions: Los Angeles, San Francisco, Sacramento, San José and unincorporated Marin. A number from that store is titled to those places, never to the United States.
  • A permit is not a completion, and a license is not an ADU grade. California licenses no ADU classification. Being named on an ADU permit is evidence of engagement in that jurisdiction, not of quality, completion, or work anywhere else. Owner-builder permits are excluded from contractor counts.
  • Calculation is labeled as calculation. Figures we derive are never presented as something HCD, HUD, the Census or a city published. Terner Center research is cited as Terner’s, never restated as ours.
  • We do not design, permit or build ADUs, and we take no payment for placement, ranking or a favorable mention. Pages that look like rankings are not: they publish public-record counts and let the reader decide.
  • Nothing here is legal, tax or financial advice. Zoning, underwriting and appraisal practice vary by jurisdiction, lender and appraiser. The useful next step on a specific lot is the planning counter and a licensed professional.

Data as of LADBS resource pi9x-tg5x retrieved 2026-09-05; feed rowsUpdatedAt 2026-08-31; observation window closes 2026-08-31; HCD APR Table A2 retrieved 2026-09-05. Authorship on this site is organizational: the analysis belongs to the desk rather than to a named individual, and we do not publish credentials we do not hold.

Our editorial policy sets out how we source, date and correct what we publish.

Sources & retrieval dates

  1. LADBS — Building and Safety Building Permits Issued from 2020 to Present (Socrata pi9x-tg5x) , 409,619 rows downloaded. The only extract this desk has found that carries an ADU flag, an issue date and a certificate-of-occupancy date on the same row. 41,374 ADU-flagged rows, 39,278 in the analysis frame after excluding 2,095 supplementals. Retrieved 2026-09-05.
  2. California HCD — Housing Element Annual Progress Report, Table A2 , The statewide cross-check. 81,853 matched permit-to-certificate project pairs, median lag 1 calendar year, 78.9% within one year. Retrieved 2026-09-05.
  3. California HCD — Table A2 CSV download , The file itself, for reproduction of the statewide lag distribution. Retrieved 2026-09-05.
  4. Chapple, Ganetsos and Lopez — Center for Community Innovation ADU owner survey (Terner-reviewed) , Survey of 2018–19 California ADU owners; 61% of new units one-bedroom, 18% studios. Cited as theirs; used here only to characterize what kind of unit these permits describe. Retrieved 2026-09-05.

Half of these projects take longer than sixteen months

A quarter of these projects have no certificate of occupancy after three years. If a schedule you have been shown assumes six months, it is not describing this distribution.

Timeline planner Read the study

HyreADU does not design, permit or build accessory dwelling units. These statistics are informational and are not construction, legal or financial advice, and they are not a schedule.

Every figure describes the City of Los Angeles unless explicitly labeled statewide; there is no national ADU construction-time series and nothing here is scaled into one.

A certificate of occupancy is a paperwork event, not a move-in date, and a permit with no final is not necessarily an abandoned project.

Headline durations are Kaplan-Meier estimates; the completed-only figures are printed beside them precisely because they are biased.